Condominio Via Busi

Rome (Italy)
350kW

This block of flats is a large residential complex consisting of 4 different buildings and a total of 59 flats. The existing technical room contained a methane boiler that generated a total power of 698kW for heating and domestic hot water production.


E.GEO has installed a vertical probe geothermal system. 350kW of geothermal energy are generated by two WBT 250G (manufactured by Teon) fed by thirty-three 130m deep double-U vertical geothermal probes.

In addition, an EIFS has been installed and doors and windows have been replaced.


Before

After